New detached mansion in Barnes, SW London

Designed during 2000-2001.
Construction commenced August 2002
completed December 2003
Architect: John E A Deacon, Architect
Structural Engineer: Chris Kendall Associates
Services Consultants: Pentangle Consulting Engineers
Quantity Surveyor: MDA Group
Main Contractor: Bowen Construction

Initial site clearance and set-up

Initial site clearance



Starting walls at east end

Starting walls




Base of internal walls

Internal walls





Internal drainage works

Drains



Bison Housebeam ground floor over east end

Ground floor





Basement slab ready for casting

basement slab





Basement top slab under construction

Basement top


Housebeam floor laid over central area

Housebeam floor





Curved lintels over flood alleviation grilles

Curved lintels





Roof timbers over annex

Roof timbers



Balcony structure underway

Balcony





Roof steelwork installed

Roof steelwork





Interior: the Music Room

Music Room





Roof coverings near completion

Roof coverings





Final snagging

Final snagging